drill cnc machine Machine parts installation and commissioning precautions?

Comments ยท 22 Views

drill cnc machine https://www.zjshuangzheng.com/Biaxial-CNC-Machine.html

Along with the development of our country's national economy and modern manufacturing industry, the use of new manufacturing equipment is a general trend, the drill cnc machine, as an important manufacturing equipment in various fields of the manufacturing industry, is becoming more and more popular to use. The new drill cnc machine must be installed and adjusted before normal operation. If the components of the drill cnc machine are improperly connected or improperly adjusted, it will result in low machining accuracy of the parts and easy failure of the machine tool, which will seriously affect the use and processing quality of the machine tool. The correct connection and debugging of new machine tools is an important guarantee for the acceptance and use of machine tools. Here is the drill cnc machine spindle bearing installation and debugging precautions to accumulate a little experience and the majority of practitioners to exchange and discuss.

(1) Installation and debugging of a single bearing: when assembling, the eccentricity of the spindle positioning hole and the spindle diameter and the eccentricity of the bearing inner ring and the raceway are close to each other as much as possible, and the direction is opposite, so that the eccentricity after assembly can be reduced.

(2) Installation and debugging of two bearings: When the main shaft bearing of two supports is installed, the eccentricity of the front and back two support bearings should be the same direction, and the size of eccentricity should be appropriately selected. The accuracy of the front bearing should be one grade higher than that of the rear bearing, so as to minimize the eccentricity of the front positioning surface of the spindle component after assembly. When the main shaft bearing is disassembled by the maintenance machine, because the original manufacturer has adjusted the eccentric position of the bearing, it is necessary to make a mark on the circular direction position before disassembly to ensure that the original relative position of the bearing and the main shaft remains unchanged after reassembly and reduce the impact on the main shaft components.

The bearing assembly of interference fit should be installed by hot loading or cold loading process method, and do not knock with brute force, so as to avoid damaging the bearing during installation and affecting the performance of the machine tool.

2, drill cnc machine ball screw nut pair installation and debugging precautions

Ball screw nut pairs are only used to withstand axial loads. The radial force and bending moment will cause the ball screw pair to produce additional surface contact stress and other undesirable loads, which may cause permanent damage to the lead screw. Therefore, when the ball screw nut pair is installed to the machine tool, attention should be paid to:

(1) The ball nut should move within the effective stroke, and the limit must be configured at both ends of the stroke to avoid the nut from the lead screw shaft and the ball falling off.

(2) Due to the high transmission efficiency of the ball screw nut pair, it can not be self-locked, when used for vertical transmission, such as the weight of the component is not balanced, it must be prevented from stopping the transmission or the reverse transmission caused by the weight of the component after the loss of power, to prevent the reverse transmission method available: worm gear and worm transmission, electric brake, etc.

(3) The axis of the lead screw must be parallel to the axis of the matching guide rail, and the center of the bearing seat at both ends of the machine tool must be in line with the center of the nut seat.

(4) When the ball screw nut pair is installed to the machine tool, do not remove the nut from the screw shaft. If it must be removed, use the auxiliary sleeve, otherwise the ball may fall off during loading and unloading.

(5) When the nut is loaded into the mounting hole of the nut seat, it is necessary to avoid impact and eccentricity.

(6) In order to prevent chips from entering and wearing the ball screw nut pair, protective devices such as crease protective cover and spiral steel belt protective cover can be added to completely protect the screw shaft. In addition, dust rings can be added to both ends of the screw nut when the floating dust is too much.

3, drill cnc machine linear rolling guide installation and commissioning precautions

(1) Handle gently during installation to avoid bumping affecting the linear accuracy of the guide rail.

(2) It is not allowed to remove the slider from the guide rail or push it back beyond the stroke. If the sliding block needs to be removed due to installation difficulties, use a guide rail.

(3) When the linear rolling guide rail is used in pairs, the main guide rail and the auxiliary guide rail are divided. The main rail pair is installed first, the reference side of the guide rail is set to be closely attached to the reference side of the installation step, and the installation bolts are tightened. Then the main rail pair is used as the reference and the auxiliary guide rail pair is installed.

drill cnc machine https://www.zjshuangzheng.com/Biaxial-CNC-Machine.html